Pressure Equipment Directive 2014/68/EU
Ensure the safety, compliance and market readiness of pressure equipment for the European market.
Overview
What is Pressure Equipment Directive 2014/68/EU
Pressure Equipment Directive (PED) Certification is a conformity assessment process that verifies that pressure equipment and assemblies comply with the requirements of the European Union’s Pressure Equipment Directive (PED) 2014/68/EU. The directive is designed to ensure the safe design, manufacture, testing, and operation of equipment that operates under pressure, helping to protect people, property, and the environment from pressure-related hazards.
The PED applies to a broad range of industries that utilize pressure-containing equipment, including oil and gas, petrochemicals, power generation, chemical processing, pharmaceuticals, food and beverage, water treatment, and manufacturing. Products such as pressure vessels, boilers, piping systems, heat exchangers, storage tanks, safety accessories, and pressure-related assemblies may fall within the scope of the directive depending on their pressure ratings and intended applications.
The regulatory framework establishes essential safety requirements, equipment categorization, conformity assessment procedures, technical documentation obligations, and CE marking requirements. Manufacturers wishing to place pressure equipment on the European Economic Area (EEA) market must demonstrate compliance with the PED and, where applicable, obtain assessment by a notified body. PED Certification provides assurance of product safety, regulatory compliance, and unrestricted access to European markets.
Products Covered
Which Products Require Pressure Equipment Directive 2014/68/EU?
The Pressure Equipment Directive (PED) applies to pressure equipment and assemblies with a maximum allowable pressure greater than 0.5 bar. Manufacturers of these products must demonstrate compliance with PED requirements before placing them on the European market.
Pressure Vessels
Pressure Vessels
Storage tanks, receivers, reactors, and other vessels designed to contain gases, liquids, or vapors under pressure.
Industrial Boilers
Industrial Boilers
Steam boilers, hot water boilers and associated pressure systems used for heating, power generation and industrial processes.
Piping Systems
Piping Systems
Industrial piping networks used to transport pressurized fluids, gases, steam, and chemicals within processing facilities.
Heat Exchangers
Heat Exchangers
Pressure-containing equipment used to transfer heat between fluids in power plants, chemical facilities, and manufacturing operations.
Safety Accessories
Safety Accessories
Safety valves, pressure relief devices, rupture discs, and protective components designed to prevent overpressure conditions.
Pressure Assemblies
Pressure Assemblies
Integrated systems consisting of multiple pressure components assembled into a functional unit, such as skid-mounted process systems.
Key Requirements
Essential Requirements for Compliance and Certification Process
To achieve PED certification, manufacturers must demonstrate that pressure equipment is designed, manufactured, tested, and documented in accordance with the essential safety requirements of the Pressure Equipment Directive (PED) 2014/68/EU. Compliance helps ensure the safe operation of pressure systems throughout their intended lifecycle.
REQUIREMENTS
Required Documents
Why Us?
Why Choose TCMS
Useful Links
FAQs
Yes. Pressure equipment falling within the scope of PED must comply with the directive before it can be legally placed on the European Economic Area (EEA) market and bear the CE marking.
PED applies to pressure vessels, boilers, piping systems, heat exchangers, safety accessories, pressure accessories, and assemblies operating at a maximum allowable pressure greater than 0.5 bar.
Industries such as oil and gas, petrochemicals, power generation, chemical processing, pharmaceuticals, food and beverage, water treatment, and manufacturing frequently use PED-compliant pressure equipment.
Yes. Depending on the equipment category and conformity assessment module, pressure testing, inspections, material verification, and non-destructive testing (NDT) may be required to demonstrate compliance.
The timeline depends on the complexity of the equipment, documentation readiness, testing requirements, and applicable assessment procedures. Certification can typically take from several weeks to a few months.
Costs vary based on equipment type, pressure category, testing requirements, manufacturing complexity, and the scope of conformity assessment. A detailed quotation is usually provided after an initial technical review.
Manufacturers typically need to provide technical drawings, design calculations, material certificates, welding procedures, inspection reports, hazard analysis, test results, operating instructions, and other supporting technical documentation.
A notified body is an independent organization authorized by the European Union to assess product conformity. Depending on the PED category, notified body involvement may be mandatory for certification and CE marking.
Once certification is completed, the manufacturer can issue the EU Declaration of Conformity, apply the CE marking, and place the pressure equipment on the European market, subject to ongoing compliance requirements.
Request Pressure Equipment Directive 2014/68/EU support